| Monday Jake spray foamed the holes in the insulation where the pipes came through and then sealed the pipes to the plastic to make an airtight barrier. |
| Tuesday morning Jake and Dad finished all the concrete rebar and reinforcing mesh placement. |
| Tuesday afternoon I joined Jake and Dad to get the garage foundation insulation started. |
| After setting up the strings again to make the building square, we finished the edge pieces. |
| Finishing up the first of two layers of insulation. By the time the sun went down we had started on the second layer. |