Garage site mostly prepped. The big board (installed by Jake) is where our electrical service will come in. |
Rebar and reinforcing mesh for our foundations. |
House site prepped for foundation. |
Measuring more than twice to make sure the foundation will be square. |
First layer of foam started. Measuring and cutting holes for the pipes slows down the process. |
First layer of foam complete. |
Specially cut sides installed. |
Close up of a corner. Luckily rocks are readily available to help hold things down. |
That's awesome! Did you have to have the foam completely custom done or is there a company that does that sort of thing?
ReplyDeleteWe'd like to add on to our basement when we do our addition and I want to foam insulate the concrete.
You guys are making great progress, keep it up!
We ordered the foam from a Canadian company called 'Legalett'. You can also have it done completely custom - there are a few companies around that provide this type of product. Theoretically you could also do it yourself - but only if you have a lot more time than money!